Earthworks and site preparation for a foundation

As at · 15 sources

What it is

Earthworks here means the ground work that comes before a foundation: clearing the site, digging out what the design says has to go, bringing in and compacting what it says has to come in, and shaping the building platform to the levels on the plans. It is the first work on site, and everything after it sits on what it leaves.

None of it starts from a guess. The ground is investigated first, and the category of the land sets how far down that investigation goes:

The ground category sets how deep the investigation goes: MBIE's guidance expects a shallow investigation for a new house on TC1 or TC2 land, and on TC3 land a site-specific deep investigation with geotechnical analysis.1

What the engineer decides

What the platform is made of, how high it sits, and what has to come out from under it. On land, for example, MBIE's guidance recommends a limit on how far a platform should rise above the land around it:

MBIE's guidance recommends that a TC2 building platform rise no more than 400 mm above the surrounding land, to limit the weight added to ground that can liquefy; more may be allowed site by site after a geotechnical investigation. Flood freeboard and insulation are not shown in the slab option details and have to be resolved separately.2

And the first of its slab options for that land starts with ground work, a gravel raft built in place of the upper soil:

For TC2 Option 1, MBIE's guidance has the upper soil dug out and replaced with compacted, well-graded gravel, placed in layers of up to 200 mm and compacted with at least a plate compactor, with the top 75 mm of AP40; poorly graded river gravels, such as tailings or 20/40 rounded stone, should not be used under it.3

Where the ground's strength is estimated from a quick test on site, MBIE's guidance singles out fill that was not engineered, and peat:

MBIE's guidance says a bearing capacity estimated from Scala penetrometer results must be adjusted for the soil type, the geometry of the foundation and the depth of the water table, and that peat deposits and non-engineered fill must always be given due regard.4

The report the design rests on has limits of its own, and what the digging finds should go back to its author:

NZGS and MBIE's guidance on geotechnical investigations says a geotechnical report should state that its recommendations rest on a limited amount of data and that conditions between the places tested may vary, and that variations found during later excavations should be passed back to the report's author.5

Which engineer answers which question:

Engineering New Zealand says you need a geotechnical engineer to assess ground conditions and decide a suitable foundation design, and to design foundations and retaining walls, and a structural engineer to assess the safety of a structure such as a retaining wall. It links a search of the register of Chartered Professional Engineers, and says being a member of Engineering New Zealand does not mean an engineer is also a CPEng.6

What happens on site

Before anything is dug, the paperwork. A project information memorandum from the council can set out resource consent requirements, ground conditions and natural hazards, and it is not a go-ahead on its own:

Christchurch City Council says a project information memorandum (PIM) is not mandatory and is not approval to start work: a building consent is still needed. The council lists what a PIM covers as including resource consent requirements, drainage and utility connections, and ground conditions and natural hazards.7

Where a large area of ground is disturbed, or a smaller one near a waterway or on a slope, the council inspects erosion and sediment control before any excavation or site clearance, and sediment control has to be in place at the foundation inspection:

Christchurch City Council allocates an erosion and sediment control inspection to high-risk sites: a disturbed area over 1,000 m², or over 500 m² within 20 m of a waterway, or over 500 m² on a slope over 5 degrees. It must take place before any excavations or site clearance. Sediment control is a minimum requirement at the foundation inspection: it must be in place, or the inspection is not passed.8

A deep excavation needs notice before anyone works in it:

WorkSafe must get 24 hours' notice before work in any pit, shaft, trench or other excavation where a person is required to work in a space more than 1.5 m deep that is deeper than it is wide at the top.9

Where the plans set a minimum floor level, a surveyor confirms the building meets it:

Where there is a minimum floor level restriction, Christchurch City Council's inspection guide says a registered surveyor must inspect and confirm, by a building location certificate, that the building will comply; the inspector may also ask for one if not satisfied about the location of the building.10

If the ground levels change from the consented plans, the consent may have to change with them:

Christchurch City Council's inspection guide gives substantive changes to ground levels that change foundations or retaining structures as an example of work that needs an amendment to the building consent.11

The building consent lists the inspections, and nothing is poured until the council has inspected the foundation:

MBIE says a building consent comes with an inspection schedule listing the inspections the council will do, which may include inspections by others, such as engineers.12Christchurch City Council's inspection called Foundation or Slab covers the pre-pour foundation, subfloor drainage and the pre-pour floor, and has to be done before concrete is poured.13

Who does what. The geotechnical engineer, and the engineer who designs the foundation, set what the ground work has to achieve; a registered surveyor confirms the floor level where the plans set a minimum, or the building's location where the council asks; and the council inspects. The digging for the foundation itself is part of what the licence for foundation work expects its holders to be able to do:

The competencies for the Foundations licence include planning and programming foundation construction, interpreting approved consent documentation, and constructing foundations “including excavation and pile construction”.14Foundation work on a house that needs a building consent is restricted building work, which a Licensed Building Practitioner licensed for that work must carry out or supervise, unless an owner-builder does it on their own home under the Act's owner-builder exemption.15

What changes the price

The price comes from your plans, the geotechnical report and the design. What moves it:

  • How much comes out, and where it goes. What the design says has to go is dug out and carted away.
  • How much goes back in, and what it is. The design sets the fill and how it is compacted.
  • The levels. How high the platform has to sit, and how much the ground has to be shaped to get it there.
  • What the digging finds. Ground that does not match the report can change what the design asks for.
  • Getting on and off the site. How machinery and trucks get in, where they can turn, and where the spoil can go.
  • Conditions on the consent, such as erosion and sediment control.

What we need from you

Ground work is priced from the same papers as the foundation it is for, whoever does it:

  • the plans, with the levels, and the engineer's foundation design;
  • the geotechnical report for the section;
  • any survey of the site, if there is one;
  • the site address, and anything that affects getting machinery onto and off the site;
  • who the builder is, if you have one.

Frequently asked

Who does the digging and the compacting?

Whoever the contracts on your job name. It can be a separate earthworks contractor, or it can be part of the foundation contract. It is worth knowing which before work starts, so it is clear who answers the engineer's questions about the ground work.

How is the ground prepared for a concrete slab?

To the design, not to a rule of thumb. The engineer's drawings and the geotechnical report say what comes out, what goes in, how it is compacted and to what levels; the gravel raft set out above is one example. Nothing is poured until the council has inspected.

What does a wet winter do to the programme?

Every step before the frames go up happens outdoors, so weather can hold up any of them. How much it holds up a job depends on the ground, the site and the weeks in question. What weather cannot do is shorten the list: the ground work still has to meet the design, and nothing is poured until the council has inspected. A step that is waiting holds up every step after it.

What we do here

UF builds pod raft foundations for TC1 and TC2 sites, and engineered foundations for TC3 sites, using Firth RibRaft, Allied SuperSlab or MAXRaft depending on what the engineer's plans specify.

Send the plans, the address and the geotechnical report if there is one. We will tell you what the ground work before a foundation involves on your section, what it is priced from, and which parts of the job are ours.

Sources

MBIE's Canterbury guidance, Part A, is published on building.govt.nz.

See also the technical category entry in the glossary.

  1. MBIE, Repairing and rebuilding houses affected by the Canterbury earthquakes, Part A, Version 3 (December 2012), Table 5.2. Checked . Read the source
  2. MBIE, Repairing and rebuilding houses affected by the Canterbury earthquakes, Part A, Version 3 (December 2012), sections 5.2 and 5.3, Figure 5.3. Checked . Read the source
  3. MBIE, Repairing and rebuilding houses affected by the Canterbury earthquakes, Part A, Version 3 (December 2012), sections 5.3 and 5.3.1, Figure 5.5. Checked . Read the source
  4. MBIE, Repairing and rebuilding houses affected by the Canterbury earthquakes, Part A, Version 3 (December 2012), section 3.4.1. Checked . Read the source
  5. NZGS and MBIE, Earthquake geotechnical engineering practice, Module 2, Geotechnical investigations for earthquake engineering, November 2021, section 5.1.5. Checked .Source: New Zealand Geotechnical Society and Ministry of Business, Innovation and Employment, Earthquake geotechnical engineering practice, Module 2 (November 2021), reproduced in part with the copyright owner's authorisation. Licence terms
  6. Engineering New Zealand, Find an engineer. Checked . Read the source
  7. Christchurch City Council, Project information memorandum (PIM). Checked .
  8. Christchurch City Council, Guide to Building Inspections (B-306), version 10 (last updated 15 June 2026), pages 4, 7 and 8. Checked .
  9. WorkSafe, Particular hazardous work (Notifiable works). Checked . Read the sourceSource: WorkSafe New Zealand, worksafe.govt.nz. © WorkSafe New Zealand; reproduced under WorkSafe's copyright terms. Licence terms
  10. Christchurch City Council, Guide to Building Inspections (B-306), version 10 (last updated 15 June 2026), page 8, Foundation or Slab. Checked .
  11. Christchurch City Council, Guide to Building Inspections (B-306), version 10 (last updated 15 June 2026), page 5, amendments. Checked . Read the source
  12. Christchurch City Council, Guide to Building Inspections (B-306), version 10 (last updated 15 June 2026), page 2 and pages 7 and 8, Foundation or Slab. Checked .
  13. Licensed Building Practitioners, What do I need to show to get my Foundations licence (factsheet), version 2. Checked . Read the sourceSource: Licensed Building Practitioners scheme (MBIE), What do I need to show to get my Foundations licence (factsheet, version 2), lbp.govt.nz. © Crown copyright. Licence terms
  14. Building Act 2004, and the Building (Definition of Restricted Building Work) Order 2011, versions as at 8 October 2026 and 15 January 2026, sections 84 and 90D; Order clauses 3 and 5. Checked .
Technical category (TC1, TC2, TC3)The categories of residential land on the flat in greater Christchurch, TC1 to TC3, as MBIE's Canterbury guidance defines them.MBIE, Repairing and rebuilding houses affected by the Canterbury earthquakes, Part A, Version 3 (December 2012) · as at 15 September 2026Read it at the sourceRead the guide