The last day: what is settled before the concrete goes in
As at
Ultimate Foundations ·
The short answer
There is one morning when your floor stops being a decision and starts being a fact. The council inspects, the trucks arrive, and by that afternoon everything in the floor, under it and shaped into it is there for as long as the house is. Nothing about that day is dramatic, which is exactly why it goes past so many people without them noticing it was the deadline.
Key points
- The pour is the last possible day, not the real deadline. The real one is when the plans go out for pricing.
- The council inspects before any concrete goes in, and the pour does not proceed without it.
- The morning of the pour is the only time anyone will ever see the inside of your floor.
What are the deadlines, working backwards?
The pour is the last possible day. The deadlines that matter are earlier, and there are three.
Before the plans are priced
This is the one that matters most, and it is the earliest.
A heated floor is a different floor — generally thicker, and that runs through the whole design. A floor that will be the finished surface is mixed, laid and cured differently from one that gets covered. Set-downs and step-free thresholds change the shape of the slab.
None of those are things you add to a quote. They change what is being quoted. Raise them after pricing and you are asking for a variation on a job already sold.
Before the boxing goes down
The shape is set here. Levels, falls, set-downs, thickenings, the rebate for a shower, the step-free line at a door.
Once the timber is in place and squared, changing the shape means pulling it apart.

Before the steel and the pods
Everything that lives inside the floor goes in now, in order: insulation, the steel, the pipes and conduit, and the heating if there is any.

This is the last hour for a spare conduit. It takes minutes and it is the cheapest thing on the whole job. After the concrete, the same pipe means cutting your floor open.
A model of the slab shows here when the page can draw it.
What happens on the morning itself?
The council's inspector comes before any concrete is poured, and looks at what is in the floor against what the engineer drew. That inspection is a gate — the pour does not go ahead without it.
Then the trucks, and often a pump, and a crew working to the weather. Once it starts it does not stop. A floor is poured in a single continuous operation, because a join in the middle of a floor is a weakness nobody wants.

What is the photograph you should keep?
The morning of the pour is the only time anyone will ever see what is inside your floor.

We take a photograph and a drawing of it before the concrete goes in — where the pipes run, where the conduit comes up, where the heating loops sit — and you keep it.
You will want it. The first time somebody drills into that floor for a wall, a fixing, a new door or a bathroom, that record is the difference between a confident job and a nervous one. It is also the answer to the question every tradesman asks about an existing slab and almost never gets.
What should be settled before that morning?
Working from the list:
- Is the floor heated, and if so, where are the zones and where does the gear live?
- Is the concrete the finished floor, or is something going on top of it?
- If it is the finished floor, what does it look like — and have you seen a real sample, dried?
- Where does power, water and data need to come up?
- Is there a spare conduit, with a string in it?
- Which doors and wet areas are step-free?
- Is anything heavy going to stand on it — a hoist, a spa, a fire?
- Is there a pad, a footing or a conduit wanted outside while the crew is here?
Does the weather decide whether it goes ahead?
It does, and the number people watch is usually the wrong one. What a fresh slab answers to is not how warm the afternoon got. It is how far the temperature falls between the pour and the next morning, because concrete moves as it cools and the first night is when it has least strength to resist that movement.
Canterbury gives that swing more room than most places. The gap between a day's high and its low is wider inland than on the coast, so the same forecast does not mean the same thing everywhere in the region.
No Canterbury council sets a temperature below which a pour may not go ahead, requires frost protection, or changes when inspections are available in winter. There is no published threshold to look up. A single number would be a poor fit for a place where the overnight fall matters more than the daytime figure, and the decision sits with the people on site on the day.
Who to contact
- A geotechnical engineer
- What the ground under your section is, and what it will carry. They investigate it and write the report the foundation is designed from.
- The engineer who designs your foundation
- What goes under the house, and why. Thickness, steel, beams and the system itself are settled here.
- Your council
- Whether the work needs a building consent, what has to be shown, and when it is inspected.
- The Licensed Building Practitioners register
- Whether the person doing restricted building work holds a licence for it. It is a free public search and it takes a minute.
- Us
- What we would build, what it would cost, and what we would need from you before we could start.
If you are told something is not possible, it is always worth asking which of these decided it. The ground and the Code are fixed. A design and a programme sometimes are not.
What we do here
If any of this is news, that is usual — most people meet the pour once. Tell us about your section and we will tell you what is still open, what your ground decides, and what has to be settled by when.
Sources
What is decided before the pour, in detail, is on what you can have in the floor of your house. How a pod raft floor goes in, and the council's inspection before the pour, is on pod raft foundations.
Why a new slab cracks, and what the joints are for, is on cracks in concrete and foundations.