What land means for a foundation, and who decides what goes under the house.
TC2 describes the land
TC2 is one of the technical categories MBIE's Canterbury guidance uses for residential land on the flat in greater Christchurch. The council describes it this way:
The council describes TC2 land as land where minor to moderate damage from liquefaction is possible in future significant earthquakes.1That puts it outside the ground the standard house foundations are written for:
MBIE's guidance says TC1 is generally regarded as the category most likely to be good ground. It says TC2 and TC3 fall outside the definition of good ground for standard residential construction, so their foundations are not within the scope of NZS 3604.2Stronger slabs for TC2 land
For a concrete slab on TC2 land, MBIE's guidance sets out stronger slabs than the standard one:
The four TC2 options in MBIE's guidance are Option 1, a reinforced NZS 3604 slab on a compacted gravel raft; Option 2, a thick slab over the existing soil; Option 3, a grid of beams with a slab, where the hardfill under the slab can be replaced with polystyrene pods; and Option 4, a waffle slab over the existing soil.3They limit how far the house deforms if the ground under it moves, and let it be brought back to level afterwards:
MBIE's guidance says the purpose of the stiffer, better-tied slabs it sets out for TC2 land is to reduce hogging and other deformation from future land damage, and to make them easier to relevel.4
The map is a starting point
The category is indicative. It comes from a map, and the map is not kept up to date:
The published technical category data describes itself as “the best information available at the time of publication on Canterbury Maps in 2017”, and says the categories “were intended to have a limited life and were not intended to be updated over time”.5You can look up an address on the category map. The geotechnical report on your section, and the engineer's design drawn from it, decide what goes under the house.
The investigation comes first
The investigation measures how much load the ground can carry. On the firmest TC2 ground, MBIE's guidance keeps timber floors on piles:
On TC2 land, MBIE's guidance uses NZS 3604 timber piles or an enhanced perimeter foundation wall where the ground is above 300 kPa, the enhanced slab Options 1 to 4 or other specific design where it is above 200 kPa, and specific design below that.7An engineer oversees the documents for MBIE's options:
MBIE's guidance says the TC2 slab Options 1 to 4 are not expected to need specific engineering design, but structural engineers must oversee their documentation; they apply to simple plan shapes and carry limits on wall and roof cladding weight.8Outside them, the foundation is for the site, and that takes more engineering.

Where pods fit
Polystyrene pods are one way to build some of MBIE's options. The options also include a slab on a gravel raft and a thick slab. The engineer decides which one goes under a house, from the investigation and the plans.
If the plans show a pod raft system, the engineer's plans say which one, and whether its own conditions fit the site. See how a pod raft goes in.
Type 2A and Type 2B are TC3 foundations
If a quote describes one as a TC2 foundation, ask which of MBIE's options it means. See what they are, and where they are used, in TC3 foundations.
The order on site
The order is the same whichever slab the engineer chooses. The building platform is prepared to the levels and depths on the plans. For MBIE's first option, that means a compacted gravel raft:
For TC2 Option 1, MBIE's guidance has the upper soil dug out and replaced with compacted, well-graded gravel, placed in layers of up to 200 mm and compacted with at least a plate compactor, with the top 75 mm of AP40; poorly graded river gravels, such as tailings or 20/40 rounded stone, should not be used under it.10On soft, variable ground, each corner of a slab bears on something different, and the differences do the damage. A dense, compacted gravel layer gives the slab one predictable thing to bear on.
Then the edges are boxed. The plumber and the electrician set their pipes and ducts where the plans put them, and the steel is placed and tied as the design shows.

What sets how long it takes
Mostly, it is the order things have to happen in. The ground is investigated first, and the design is drawn from the investigation. Nothing is poured until the council has inspected, with the engineer's inspections where the consent calls for them:
MBIE says a building consent comes with an inspection schedule listing the inspections the council will do, which may include inspections by others, such as engineers.11What moves the price
The price comes from your plans, the geotechnical report and the engineer's design. On TC2 land, these move it:
- The ground, and which slab it allows. Digging out soil for a gravel raft, a thicker slab, and a slab over polystyrene pods are different amounts of work and material.
- The house. Heavy cladding such as brick veneer, a second storey or an irregular plan changes the slab, or takes the house outside MBIE's options altogether.
- Access and earthwork. How machinery and concrete trucks reach the platform, and how much earthwork it needs.
- What is cast into the slab. Services, set-downs for showers, garage doors or brick veneer, and any insulation the drawings show.

What we need from you
To price a pod raft foundation on TC2 land we need:
- the plans, and the engineer's foundation design if there is one yet;
- the geotechnical report for the section;
- the site address, and anything we should know about getting onto the site;
- who the builder is, if you have one.
What we do here
Send the plans and the geotechnical report. We will tell you which of the options the report points to, and what the engineer settles.
Sources
- Christchurch City Council, Technical categories information. Checked . Read the source
- MBIE, Repairing and rebuilding houses affected by the Canterbury earthquakes, Part A, Version 3 (December 2012), section 3.1. Checked . Read the source
- MBIE, Repairing and rebuilding houses affected by the Canterbury earthquakes, Part A, Version 3 (December 2012), section 5.3.1. Checked . Read the source
- MBIE, Repairing and rebuilding houses affected by the Canterbury earthquakes, Part A, Version 3 (December 2012), section 5.2. Checked . Read the source
- Environment Canterbury, MBIE Technical Categories dataset, description (data.govt.nz catalogue). Checked . Read the sourceSourced from Canterbury Maps and partners and licensed for reuse under the CC BY 4.0 licence (MBIE Technical Categories; item credit: Canterbury Earthquake Recovery Authority); quoted in part. Licence terms
- MBIE, Repairing and rebuilding houses affected by the Canterbury earthquakes, Part A, Version 3 (December 2012), section 3.4.1 and Table 5.2. Checked . Read the source
- MBIE, Repairing and rebuilding houses affected by the Canterbury earthquakes, Part A, Version 3 (December 2012), Table 5.2. Checked . Read the source
- MBIE, Repairing and rebuilding houses affected by the Canterbury earthquakes, Part A, Version 3 (December 2012), sections 5.2 and 5.3. Checked . Read the source
- MBIE, Repairing and rebuilding houses affected by the Canterbury earthquakes, Part C, Version 3a (April 2015), section 15.4.4. Checked . Read the source
- MBIE, Repairing and rebuilding houses affected by the Canterbury earthquakes, Part A, Version 3 (December 2012), sections 5.3 and 5.3.1, Figure 5.5. Checked . Read the source
- MBIE, Guide to applying for a building consent and code compliance certificate, Third edition (October 2022), Step 5, Inspections and code compliance certificate. Checked .Source: Ministry of Business, Innovation and Employment, Guide to applying for a building consent and code compliance certificate (October 2022). © Crown copyright. Licence terms