What goes inside the floor

As at

The short answer

A concrete floor is not solid the way it looks. Running through it, under it and up out of it is everything the house needs to come up from below — water, waste, power, data, heating, ducting. All of it is placed before the concrete, and none of it can be added afterwards without cutting.

Key points

  • Everything that comes up through a floor is placed before the concrete. Afterwards it is a cutting job.
  • A spare empty pipe with a string in it is the cheapest thing on the job and almost nobody is offered one.
  • A step is not a fitting. It is the shape of the concrete, and the shape is poured once.

A model of the slab shows here when the page can draw it.

What is the cheapest thing on the whole job?

A spare empty pipe, with a string already threaded through it.

It goes in with everything else, it takes minutes, and it costs very little while the boxing is down. It runs from somewhere sensible — a wall cavity, the garage, the switchboard — to somewhere else sensible, and then it sits there empty.

You do not have to know what it is for. That is the entire point of the string. Whatever you want to run through that floor later, the string pulls it through.

Without it, the same job means cutting a finished floor open, making good, and living with the line where it was.

We cast it in. The next trade connects it. We put the pipe in before the concrete goes down; your electrician or your plumber connects to it whenever you are ready.

What do people wish they had put in?

Every one of these is a pipe or a duct, and every one is cheap now and a cutting job later.

A charger in the garage. A conduit to the garage wall is a few dollars of pipe today. Almost everybody will want one within the life of the house, and retrofitting means opening the floor.

Solar and a battery. A run from the roof to the board to wherever a battery might live.

Network cable. To a hub, and out to the places that will want it. Wireless is fine until it is not, and a house full of concrete and steel is not the friendliest place for it.

A rainwater tank. The feed from the downpipes, the overflow, and the point a pump will stand. Tanks go in for the garden, for stock water, and sometimes because the consent asks for one. All three runs are trenching once the slab and the paving are down.

Central vacuum ducting. The least recoverable thing on this list. The pipework runs inside the floor and up inside the walls, and once both are closed there is nowhere left for it to go.

Power and water outside. To the patio, the shed, the garden, the spot where the outdoor kitchen will go one day. Getting services past a finished slab and finished landscaping is the expensive version.

Ducting for whole-house ventilation, or for ducted heating, has to run somewhere. Under the floor is often the sensible place and the only available moment.

A drain where you will want one. A wash bay, a workshop, somewhere to hose the dog, the boat or the boots. A drain is a fall in the concrete, not a fitting — so it is shaped in, not added.

A garage floor that drains. A wet car, a hosed-out floor, a washing machine that lets go. Water goes where the floor falls, and the floor falls where it was shaped to fall — towards a drain, or out the door, or into the corner by the internal door if nobody thought about it.

A pad and a drain for the heat pump. The unit outside stands on something and drips somewhere. Both are decided now or bodged later.

Why is a step not a fitting?

Because it is the shape of the concrete, and the shape of the concrete is poured once.

A shower with no lip. The floor drops into the wet area and drains, and there is nothing to step over. Done in the boxing, weeks before anyone chooses a tile.

A door to the patio with no drop. Inside floor and outside paving at the same level, so the door opens onto the patio rather than above it. It is the difference between a deck you use and a step you step down.

An entry with no step at all. A pram, a wheelchair, a walking frame, a delivery on a trolley. Nobody plans this for themselves while they are young and fit. Plenty of people need it later, in the same house they built without it.

A lift pit, if a lift is even a maybe. A platform lift sits in a shallow recess in the floor. Formed before the pour it is boxing. Cut afterwards it is a hole in a structural slab, and that is the engineer's decision before it is anybody else's.

Tiled rooms that finish flush with the rest of the floor, instead of a lip at every doorway.

All of it is a set-down — a deliberate drop in the slab where something thicker is going on top. It costs nothing extra in concrete. It costs a great deal to add later.

A cut through a floor slab. On the left the slab top is at one height. On the right it steps down, and the thickness of a tile and the bed under it fills the step, so the finished tiled surface arrives level with the floor on the left. A dashed line runs across both to show the single finished level.

A model of the slab shows here when the page can draw it.

What if something heavy is going to stand on it?

Say so before the steel goes in.

A car hoist. A spa full of water and people. A wood fire or a heavy range. A wall that might get built one day where there is not one now. Each of those wants a thicker, stronger patch of floor under it — and a thicker patch is a design decision the engineer makes, not something we decide on site.

Cheap while the floor is being designed. A structural problem afterwards.

What else is worth pouring at the same time?

Not everything that wants concrete is part of the house.

A bin pad. Somewhere flat and hard for the bins to stand, instead of grass, or a slope on collection day.

A base for a water tank. A full tank is heavy, and it has to sit level on something that will not settle under it. A tank on bare ground finds that out slowly.

A pad at the back door, the shed door, the gate. The places you walk every day in the rain.

Footings for the things that come later. A deck, a pergola, a carport, a shade sail, the fence, the gate, the letterbox. Each one needs a hole with concrete in it, and it is the same hole whether it is dug now or long after the house is finished.

A slab for the sleepout or the second garage you have drawn but not built. If it is on the plan and the ground is already open, it is one setting out instead of two.

None of these is big. That is the point: each one is a small area of flat concrete while the foundation work is already happening, and a separate small job with its own setup afterwards.

Ask for them on the same drawing as the foundation.

How will anyone know where it all is?

The morning of the pour is the only time anybody will ever see the inside of your floor.

Reinforcing mesh on chairs over membrane with pink set-out marks, a paddock and mountains beyond

We photograph it and draw it before the concrete goes in, and you keep that record. The first time somebody needs to drill, cut or fix into that floor, it is the difference between a confident job and a nervous one.

What might your ground say about it?

Penetrations through a slab — every pipe, every conduit — are holes in a structure the engineer designed. Where they go and how many there are is not unlimited, and on ground that moves the design is tighter.

If you are told no, ask who decided. The geotechnical engineer, the structural engineer, the council and the build programme are four different answers, and only some of them are fixed.

Who to contact

A geotechnical engineer
What the ground under your section is, and what it will carry. They investigate it and write the report the foundation is designed from.
The engineer who designs your foundation
What goes under the house, and why. Thickness, steel, beams and the system itself are settled here.
Your council
Whether the work needs a building consent, what has to be shown, and when it is inspected.
The Licensed Building Practitioners register
Whether the person doing restricted building work holds a licence for it. It is a free public search and it takes a minute.
Us
What we would build, what it would cost, and what we would need from you before we could start.

If you are told something is not possible, it is always worth asking which of these decided it. The ground and the Code are fixed. A design and a programme sometimes are not.

What we do here

Bring the list, even a rough one — a charger eventually, a tap out the back, a shower with no step, and a spare pipe because who knows. Bring the things that are not part of the house as well: the deck that is coming, the shed, the bins, the fence. We will tell you what your ground and your design allow, what it changes, and who has to be involved in each.

Sources

The deadlines before a pour, and what the council checks on the morning, are on the last day. The rest of what is decided before the concrete is on what you can have in the floor of your house.