Drilling, coring and cutting a concrete slab: what could be inside
As at · 13 sources
Ultimate Foundations ·
The short answer
A concrete floor slab can hold more than concrete: reinforcing steel and, depending on how it was built, polystyrene pods with concrete ribs between them, service pipes, and in some slabs steel strands held under tension. A drill, a core or a saw can hit any of them. Before anyone cores or cuts through a slab, ask a structural engineer whether and where it can be done, and ask the council whether the work needs a building consent.
Key points
- B1/AS1 (Structural provisions for buildings), in its second edition in effect from 28 July 2025, changes NZS 3604 so that all slab-on-ground floors must be reinforced concrete. B1/AS1 is an acceptable solution: one way to comply with the Building Code.1
- MBIE's TC2 Option 3, a grid of beams with a slab, has a post-tensioned variation, and the guidance says that variation requires specific engineering design.2
- One pod floor system's technical manual allows service pipes to run in two ways: inside the slab, within the layer of pods, crossing the ribs and beams rather than running along them; or under the slab, brought up through a pod. Where a pipe crosses a rib or edge beam, it goes through the middle third of its depth.3
What could be inside a concrete slab?
Steel, first. A slab built to today's acceptable solution is reinforced concrete, but what is in an older slab depends on the rules when it was built.
MBIE's guidance says house slabs designed to NZS 3604 before the 2011 citation update may or may not be reinforced, with mesh, polypropylene fibre or reinforcing bar, and that from 1990 to 2011 single-storey slabs could be built with no reinforcing steel. Before 1978, it says, a slab could sit on its foundation without being connected to it.4In a pod floor, the slab is poured over polystyrene pods, with concrete ribs between them; Pod raft foundations shows how one goes together. One pod floor system's manual allows service pipes to run through the slab among the pods, or under it, as the key points above set out. Below the concrete there may also be a .
What is a post-tensioned slab?
A slab with steel strands running through it that are pulled tight with jacks and anchored at both ends, at the slab's edges. MBIE's guidance for Canterbury houses describes how one is built, and where one can be used:
MBIE's guidance describes how the post-tensioned slab it sets out for TC2 land is built: the steel strands come factory-greased and sheathed in plastic, sit on bar chairs in the slab, and are tensioned with hydraulic jacks through mono-strand anchorages fixed at both ends through the perimeter formwork.5 MBIE's guidance for TC3 land says the reinforced concrete underslab of some surface structures could be post-tensioned to improve its out-of-plane stiffness, and notes that stressing a slab is a specialised process.6Whether your slab is one is a question for a structural engineer.
Can you drill or cut into a post-tensioned slab?
Whether a slab that could be post-tensioned can be drilled, cored or cut at all, and where, is a structural engineer's call on the slab itself. The strands in it are under tension.
Who decides which cuts a slab can take?
A structural engineer, on the slab in front of them.
Engineering New Zealand says you need a geotechnical engineer to assess ground conditions and decide a suitable foundation design, and to design foundations and retaining walls, and a structural engineer to assess the safety of a structure such as a retaining wall. It links a search of the register of Chartered Professional Engineers, and says being a member of Engineering New Zealand does not mean an engineer is also a CPEng.7Does cutting or coring a slab need a building consent?
Whether a hole, cut or core in your slab needs a building consent depends on its size, the building and what it affects. The Building Act exempts some holes for pipes and cables:
Schedule 1 of the Building Act exempts from needing a building consent the making of a penetration of up to 300 millimetres in diameter for pipes, cables, ducts, wires, hoses and the like, with associated work such as weatherproofing, fireproofing or sealing, through an existing dwelling that is detached or in a building of no more than 3 storeys, or through a detached outbuilding of no more than 3 storeys. Through any other existing building the penetration must also not modify or affect the building's primary structure or any specified system.8Exempt or not, the work has to meet the Building Code:
The Building Act requires all building work to comply with the Building Code to the extent the Act requires, whether or not it needs a building consent. An exemption in Schedule 1 applies only on conditions that include the work complying, the building complying afterwards at least as well as it did before, and the work breaching no other enactment.9Ask before the work starts. The council is one of the advisers MBIE lists:
MBIE lists who can advise whether building work is exempt from needing a building consent: the building consent authority (usually the council, which may charge), a registered architect, a chartered professional engineer, a registered building surveyor, a building consultant, a registered electrician, a licensed building practitioner holding the relevant licence class, a registered certifying plumber or drainlayer, and an independent qualified person.10Will the council's property file show what is in the slab?
It might, and it is the cheapest place to start. Where work was consented, the council's property file may hold the plans and specifications, the code compliance certificate and the drainage plans for that work. If consented drawings exist for your slab, that is the first documentary check on what was built.
What the council will not give you is a promise. Christchurch City Council says a property file may include those things — a list of what a file can hold, not an undertaking that yours holds them, and it says plainly that it cannot guarantee the information you need will be there. For the oldest houses it is unlikely to hold the original plans at all, and for some categories of housing it holds none.
So the file is the first place to look, not the answer. What it cannot tell you is still a question for someone who can see the slab.
Can a scan show what is inside a slab?
Ask the structural engineer what they need to know about the slab before it is cut, and how they want it found out.
What does WorkSafe say about dust from cutting concrete?
WorkSafe names concrete among the materials that contain silica, and drilling and cutting it among the tasks that make silica dust:
WorkSafe says silica is found in concrete, bricks, rocks, stone, sand and clay, and that respirable crystalline silica dust “is created when materials containing silica are cut, ground, drilled, sanded, polished or otherwise disturbed”. The construction tasks it lists include “concrete drilling, cutting, grinding”.11It also sets out how the dust is controlled at the tool, and where a respirator sits among the controls:
WorkSafe says tools for cutting, grinding or polishing concrete and masonry “should provide water to the blade and/or be fitted with an on-tool extraction system”, and that personal protective equipment, such as a respirator, is “the least effective control measure”, not the first or the only one.12 WorkSafe's guidance on on-tool extraction says crystalline silica dust calls for an H-class vacuum, adding “This includes working in someone's home”, and that workers should not use a household vacuum cleaner for this dust.13Who to contact
- A geotechnical engineer
- What the ground under your section is, and what it will carry. They investigate it and write the report the foundation is designed from.
- The engineer who designs your foundation
- What goes under the house, and why. Thickness, steel, beams and the system itself are settled here.
- Your council
- Whether the work needs a building consent, what has to be shown, and when it is inspected.
- The Licensed Building Practitioners register
- Whether the person doing restricted building work holds a licence for it. It is a free public search and it takes a minute.
- Us
- What we would build, what it would cost, and what we would need from you before we could start.
If you are told something is not possible, it is always worth asking which of these decided it. The ground and the Code are fixed. A design and a programme sometimes are not.
What we do here
UF builds pod raft foundations for and TC2 sites, and engineered foundations for TC3 sites, using Firth RibRaft, Allied SuperSlab or MAXRaft depending on what the engineer's plans specify. If you are building, send the plans and the address.
Sources
To find a chartered professional engineer, use the register search from Engineering New Zealand.
- MBIE, B1/AS1 Structural provisions for buildings, Second Edition, Preface and paragraphs 2.3.7.1 to 2.3.7.3. Checked . Read the source
- MBIE, Repairing and rebuilding houses affected by the Canterbury earthquakes, Part A, Version 3 (December 2012), section 5.3.1, Figures 5.7 to 5.9. Checked . Read the source
- Firth, RibRaft Technical Manual, October 2024, Section 1, clauses 6.5 to 6.7 and Table 6. Checked .
- MBIE, Repairing and rebuilding houses affected by the Canterbury earthquakes, Part A, Version 3 (December 2012), Appendix A4.2.2 and A4.2.4. Checked . Read the source
- MBIE, Repairing and rebuilding houses affected by the Canterbury earthquakes, Part A, Version 3 (December 2012), section 5.3.1, Figure 5.9 and its note. Checked . Read the source
- MBIE, Repairing and rebuilding houses affected by the Canterbury earthquakes, Part C, Version 3a (April 2015), section 15.4.4. Checked . Read the source
- Engineering New Zealand, Find an engineer. Checked . Read the source
- Building Act 2004, version as at 8 October 2026, Schedule 1, clause 14. Checked . Read the source
- Building Act 2004, version as at 8 October 2026, sections 17 and 42A. Checked . Read the source
- MBIE, Building work that does not require a building consent, 6th edition, version 2 (January 2026), Ask for advice. Checked .Source: Ministry of Business, Innovation and Employment, Building work that does not require a building consent (6th edition, version 2, January 2026). © Crown copyright. Licence terms
- WorkSafe New Zealand, Silica dust in the workplace, last updated 13 January 2020. Checked . Read the sourceSource: WorkSafe New Zealand, worksafe.govt.nz. © WorkSafe New Zealand; reproduced under WorkSafe's copyright terms. Licence terms
- WorkSafe New Zealand, Silica dust in the workplace, last updated 13 January 2020. Checked . Read the sourceSource: WorkSafe New Zealand, worksafe.govt.nz. © WorkSafe New Zealand; reproduced under WorkSafe's copyright terms. Licence terms
- WorkSafe New Zealand, Controlling dust with on-tool extraction. Checked . Read the sourceSource: WorkSafe New Zealand, worksafe.govt.nz. © WorkSafe New Zealand; reproduced under WorkSafe's copyright terms. Licence terms
Page history
Current as at .