Repiling and underpinning: what each involves, and who decides
As at · 19 sources
Ultimate Foundations ·
The short answer
Repiling replaces the piles under a timber floor that have rotted, sunk or been damaged. Relevelling jacks the sunken parts of a floor back towards level and packs or replaces the piles to hold it there. Underpinning is named in MBIE's Canterbury guidance as one way to support a damaged foundation, beside improving the ground and replacing the foundation. Which of these a house needs, if any, is for a structural engineer who has seen it, and whether the work needs a building consent is for the council.
Key points
- For houses whose timber floors sit on piles alone, on TC1 and TC2 land, MBIE's Canterbury guidance says local settlement or pile damage can be addressed by repacking, pile replacement or both, as appropriate.1
- The Licensed Building Practitioners scheme says “A minor repair to a few piles might not need one [a building consent], but it pays to check with the local Building Consent Authority, or read MBIE's guidance on Schedule 1”, and that anyone unsure of the method or the consent position should speak to the building consent authority, and consult an engineer for expert advice.2
- MBIE's Canterbury guidance says relevelling foundations and floor slabs by any of the options listed in its Appendix A1 is building work, and that underpinning grout or engineered resin forms part of the foundation system.3
Why do floors in older houses go out of level?
BRANZ's guidance for older houses looks under the floor: at the piles, at the ground under them, and at work done on them before.
BRANZ's Renovate guidance gives these causes of uneven floors in older houses: rotten or deteriorated timber piles; piles or bearers removed in past alterations; soft ground letting piles sink; a previous repile that was not levelled; and over-spanned joists. It says that in cases of subsidence you should get advice from a qualified structural engineer.4What is repiling?
Replacing piles that have rotted, sunk or been damaged, with new piles that hold the floor up again.
BRANZ's Renovate guidance says rotted timber piles are replaced with H5 treated timber or precast concrete piles, installed from under the floor where there is at least 450 mm clear, or through holes about 450 mm square cut in the floor; that earthquake bracing may also be needed; and that in soft ground deeper piles may be needed.5MBIE's Canterbury guidance, written after the earthquakes, treats packing the piles and replacing them as the local repairs for a floor on piles, as the key points above quote.
What is relevelling, or jack and pack?
Jacking the parts of a floor that have sunk back towards level, then packing or replacing the piles to hold it there.
BRANZ's Renovate guidance says the most effective correction of an uneven floor is for a firm experienced in the work to jack the sunken parts back to as near level as possible, then replace piles and damaged subfloor to hold the building there, and that this may damage linings and need doors and windows adjusted.6How is a concrete foundation or slab lifted?
By jacking it, or by injecting something into the ground beneath it. MBIE's Canterbury guidance sets out the methods:
MBIE's Canterbury guidance sets out four methods of lifting a settled foundation, which it says have all been used extensively over many years to relevel foundations that have settled: jacking the perimeter wall with portable jacks and filling the cavity with grout; jacking off screw piles installed along the wall, which may also stay as permanent support; injecting an expanding engineered resin into the ground; and injecting low-mobility grout into the ground beneath the foundation.7The guidance counts relevelling by any of them as building work, and the grout or resin left in the ground as part of the foundation, as the key points above quote.
What is underpinning?
MBIE's Canterbury guidance names pile underpinning among the possible methods where a damaged house keeps a heavy roof or cladding, and ties it to an investigation of the ground:
Where heavy roofs or claddings are kept on a TC3 house despite foundation damage and poor house or ground performance, MBIE's Canterbury guidance lists possible methods as pile underpinning, ground improvement, foundation replacement or the like, and says this will need an appropriate level of geotechnical investigation.8Where a relevel uses permanent deep piles, the guidance says what has to sit on them:
Where relevelling uses permanent deep piles, MBIE's Canterbury guidance says at least all perimeter foundation elements and load-bearing walls should be supported on those piles, to prevent future gross differential movement, and that internal non-loadbearing timber floors left on shallow piles may need relevelling or packing in future.9Do I need building consent to repile a house?
Ask the council, before the work starts, whether your job needs a consent. The Building Act exempts some repair and replacement work, but not the complete or substantial replacement of a part that contributes to the structure:
Schedule 1 of the Building Act exempts from needing a building consent the repair and maintenance of a building product or assembly using a comparable one, and its replacement with a comparable product or assembly in the same position. The exemption does not cover the complete or substantial replacement of a specified system, or of a product or assembly that contributes to the building's structural behaviour or fire-safety properties; the repair or replacement, other than maintenance, of something that has failed the Building Code's durability provisions; or sanitary plumbing or drainlaying under the Plumbers, Gasfitters, and Drainlayers Act 2006.10Your council can also decide that a particular job does not need one:
Schedule 1 of the Building Act also lets the council exempt any building work from needing a building consent where it considers the completed work is likely to comply with the Building Code or, if it would not comply, is unlikely to endanger people or any building.11Exempt or not, the work has to meet the Building Code:
The Building Act requires all building work to comply with the Building Code to the extent the Act requires, whether or not it needs a building consent. An exemption in Schedule 1 applies only on conditions that include the work complying, the building complying afterwards at least as well as it did before, and the work breaching no other enactment.12Advice from the Licensed Building Practitioners scheme is in the key points above, and MBIE's guide for Canterbury builders says the same about structural repairs:
MBIE's guide for Canterbury builders on below-floor work lists repairs or replacement of structural components among the work that must have a building consent, noting that some minor structural repairs may not need one and that you should check with the local building consent authority.13Who does the work, and who designs it?
Where the work needs a building consent, foundation work on a house is restricted building work, and the practitioner who does or supervises it gives a record of work when their part is finished:
Foundation work on a house that needs a building consent is restricted building work, which a Licensed Building Practitioner licensed for that work must carry out or supervise, unless an owner-builder does it on their own home under the Act's owner-builder exemption.14 Under the Building Act, each licensed building practitioner who carries out (other than as an owner-builder) or supervises restricted building work under a building consent must, when that work is complete, give the owner and the council a record of work in the prescribed form, stating the restricted building work they carried out or supervised. The same applies to restricted building work on a small stand-alone dwelling built without a consent, where the record goes to the owner and the council that issued its project information memorandum. A record of work does not by itself create any liability, or a civil liability to the owner that would not otherwise exist.15Pile foundations are one of the two areas of the Foundations licence for licensed building practitioners:
The Foundations licence for Licensed Building Practitioners has two areas of practice: “Foundations 1: Concrete foundation walls and concrete slab-on-ground” and “Foundations 2: Concrete or timber pile foundations”.16 Anyone can check a Licensed Building Practitioner in two ways: ask to see their current licence ID, which carries a code that shows their credentials, or search the public register. The scheme says to make sure the practitioner is licensed in the correct class for the work.17Where the design of a repair is non-standard, it is usually an engineer's:
MBIE's guide for Canterbury builders on below-floor work says specific engineering design is needed where the design or design method is non-standard, meaning outside the Acceptable Solution or Verification Method, and that it will usually be done by a Chartered Professional Engineer (CPEng).18 Engineering New Zealand says you need a geotechnical engineer to assess ground conditions and decide a suitable foundation design, and to design foundations and retaining walls, and a structural engineer to assess the safety of a structure such as a retaining wall. It links a search of the register of Chartered Professional Engineers, and says being a member of Engineering New Zealand does not mean an engineer is also a CPEng.19Who to contact
- A geotechnical engineer
- What the ground under your section is, and what it will carry. They investigate it and write the report the foundation is designed from.
- The engineer who designs your foundation
- What goes under the house, and why. Thickness, steel, beams and the system itself are settled here.
- Your council
- Whether the work needs a building consent, what has to be shown, and when it is inspected.
- The Licensed Building Practitioners register
- Whether the person doing restricted building work holds a licence for it. It is a free public search and it takes a minute.
- Us
- What we would build, what it would cost, and what we would need from you before we could start.
If you are told something is not possible, it is always worth asking which of these decided it. The ground and the Code are fixed. A design and a programme sometimes are not.
What we do here
UF builds pod raft foundations for and TC2 sites, and engineered foundations for TC3 sites, using Firth RibRaft, Allied SuperSlab or MAXRaft depending on what the engineer's plans specify. If you are building, send the plans and the address.
Sources
MBIE's Canterbury guidance, Parts A and C, and its guide for Canterbury builders on below-floor work are published on building.govt.nz. Advice from the Licensed Building Practitioners scheme on relevelling piles is on its jack and pack page. BRANZ sets out repiling and levelling for older houses on its Renovate site. To find a chartered professional engineer, use the register search from Engineering New Zealand.
- MBIE, Repairing and rebuilding houses affected by the Canterbury earthquakes, Part A, Version 3 (December 2012), section 4.2. Checked . Read the source
- Licensed Building Practitioners, Codewords 74, Doing it right with jack and pack, September 2016. Checked . Read the sourceSource: Licensed Building Practitioners scheme (MBIE), lbp.govt.nz. © Crown copyright. Licence terms
- MBIE, Repairing and rebuilding houses affected by the Canterbury earthquakes, Part A, Version 3 (December 2012), section 4.3.1, Building Code issues. Checked . Read the source
- BRANZ Renovate, Villa, Foundations and subfloors, Repiling and levelling; Bungalow, Uneven floors. Checked . Read the source
- BRANZ Renovate, Villa, Foundations and subfloors, Repiling and levelling (Repiling). Checked . Read the source
- BRANZ Renovate, Villa, Foundations and subfloors, Repiling and levelling (Levelling). Checked . Read the source
- MBIE, Repairing and rebuilding houses affected by the Canterbury earthquakes, Part A, Version 3 (December 2012), Appendix A1, Figures A1.1 to A1.4. Checked . Read the source
- MBIE, Repairing and rebuilding houses affected by the Canterbury earthquakes, Part C, Version 3a (April 2015), sections 14.2.1 and 14.2.2. Checked . Read the source
- MBIE, Repairing and rebuilding houses affected by the Canterbury earthquakes, Part C, Version 3a (April 2015), section 14.2.2. Checked . Read the source
- Building Act 2004, version as at 8 October 2026, Schedule 1, clause 1. Checked . Read the source
- Building Act 2004, version as at 8 October 2026, Schedule 1, clause 2. Checked . Read the source
- Building Act 2004, version as at 8 October 2026, sections 17 and 42A. Checked . Read the source
- MBIE, The guide for Canterbury builders, Below-floor work, April 2013, page 9. Checked . Read the source
- Building Act 2004, and the Building (Definition of Restricted Building Work) Order 2011, versions as at 8 October 2026 and 15 January 2026, sections 84 and 90D; Order clauses 3 and 5. Checked .
- Building Act 2004, version as at 8 October 2026, section 88(1), (1A), (2) and (4). Checked . Read the source
- Licensed Building Practitioners, What do I need to show to get my Foundations licence (factsheet), version 2. Checked . Read the sourceSource: Licensed Building Practitioners scheme (MBIE), What do I need to show to get my Foundations licence (factsheet, version 2), lbp.govt.nz. © Crown copyright. Licence terms
- Licensed Building Practitioners, Find an LBP. Checked . Read the sourceSource: Licensed Building Practitioners scheme (MBIE), lbp.govt.nz. © Crown copyright. Licence terms
- MBIE, The guide for Canterbury builders, Below-floor work, April 2013, pages 6 to 8. Checked . Read the source
- Engineering New Zealand, Find an engineer. Checked . Read the source