Dairy shed floors: a floor that is hosed twice a day and walked by every cow you own

As at

The short answer

A dairy shed floor is not a building floor that happens to have cows on it. It is a working surface that is wet twice a day, washed with serious volumes of water, walked by stock in single file at the same pinch points every milking, and expected to drain completely — because water that stands becomes effluent that stands. Nearly everything that makes one work is decided before the pour.

Key points

  • Falls are the whole job. A milking floor either sheds water everywhere, or it holds it somewhere, and which one you get is set in the formwork.
  • Stock walk the same lines every day. Where the surface needs grip, and where it needs to be easy to scrape and hose, are different places — and both are finishing decisions made at the pour.
  • A lot of the best dairy-shed work is not a new shed. It is putting right the floor in one that is already milking, which is a staging problem as much as a concrete one.

What makes a milking floor different from any other floor?

Water, stock and repetition.

The floor is washed down after every milking, so every square metre needs somewhere for that water to go, at a fall that actually takes it there. Cows walk it in the same lines twice a day, so the surface wears where they walk and stays green where they do not. And the same few places — the entry, the exit, the pit edge, the gates — take almost all of the punishment.

A floor laid out for the hose and the herd lasts. A floor laid out like a warehouse slab with drains added at the end fights you every single day it is in service.

Where does the water need to go?

Everywhere, by design — and that is set in the formwork, not the finishing.

Falls on a milking floor are not one slope to one drain. The platform, the pit surrounds, the holding areas and the exit all want their own falls, meeting at channels and sumps placed where the wash-down actually happens rather than where a drawing found convenient. Nibs and kerbs decide where water and effluent are allowed to travel, and they are formed and poured, not bolted on.

Get the falls right and wash-down is a few minutes of hose. Get them wrong and somebody pushes water uphill with a squeegee twice a day for the life of the shed.

Why does the surface matter so much — and where?

Because a cow that slips once baulks at that spot for a season.

Where stock walk, the surface needs honest grip — a finish chosen for hooves and wet concrete, not for looks. Where the hose and the scraper do the work, it wants to be smooth enough to clean fast. Those two needs sit side by side in the same building, sometimes within a metre of each other, and the switch from one to the other is decided while the concrete is wet. It cannot be traded afterwards without grinding or topping — which is exactly the kind of fixing-an-existing-floor work we are asked to do, and would rather you never need.

Your milk company's supply terms set requirements of their own for the shed and its surfaces. Check what yours asks for before anything is drawn, because it is cheaper to meet a requirement in the boxing than to argue with it after the pour.

What about a shed that is already milking?

This is more of the work than anyone advertises, and it is as much programme as concrete.

Floors in working sheds wear hollow where the herd walks, hold water where they have settled, and break up at pit edges and gateways. The job is diagnosing why before deciding what: re-laying falls that never worked is a different fix from repairing a surface that simply wore out. And all of it has to happen between milkings or in the dry period, staged so the shed never stops working — which is a plan made before anyone cuts anything.

If the floor fights you every day, that is worth a conversation this season, not next: floors do not improve on their own, and the dry period is the window.

When can stock walk on new concrete?

When it is ready — and what decides that is the mix, the weather and the temperature on the days after the pour, not a number read off a calendar.

Anyone who gives you one answer for July and the same answer for January is reading a habit, not the concrete. Ask us for the honest answer for your pour, in your month, and plan the milking around that rather than around hope.

Who to contact

A geotechnical engineer
What the ground under your section is, and what it will carry. They investigate it and write the report the foundation is designed from.
The engineer who designs your foundation
What goes under the house, and why. Thickness, steel, beams and the system itself are settled here.
Your council
Whether the work needs a building consent, what has to be shown, and when it is inspected.
The Licensed Building Practitioners register
Whether the person doing restricted building work holds a licence for it. It is a free public search and it takes a minute.
Us
What we would build, what it would cost, and what we would need from you before we could start.

If you are told something is not possible, it is always worth asking which of these decided it. The ground and the Code are fixed. A design and a programme sometimes are not.

What we do here

Tell us what the floor is doing to you — where it holds water, where the herd baulks, what the wash-down takes — or send the plans if it is a new shed, along with what your milk company's terms require. We will tell you what is a falls problem, what is a surface problem, what is structural and needs your engineer, and how the work can be staged around milking.

Sources

This page is written from the work itself. Your milk company's supply terms and your council's consent requirements are the documents that govern your shed, and they are the ones to read beside it. The rest of the farm work is on concrete on the farm.